Construction Journal

Construction Journal

August 2026

Building 1: Plastering and skimming works continued, as did installation works and ceramic tiling in bathrooms and kitchens. Installation of interior apartment doors began. Washable painting works continued, and parquet flooring installation began. Ceramic flooring installation in common areas continued, along with thermal insulation works and facade finishing works. Exterior railings are being installed, and terrace flooring installation continued;
Building 2: Plastering works and installation works continued. Parquet flooring installation began. Tiling (floor and wall tiles) continued, as did thermal insulation and facade finishing works. Exterior railings are being installed, and terrace flooring installation continued;
Building 3: Plastering and skimming works continued, as did installation works. Ceramic tiling in bathrooms and kitchens continued. Washable painting works, interior apartment door installation, and parquet flooring installation began. Ceramic flooring installation in common areas continued, along with thermal insulation works and facade finishing works. Exterior railings are being installed, and terrace flooring installation began.

July 2026

Building 1: Plastering and skimming works continued, as did installation works and ceramic tiling in bathrooms and kitchens. Washable painting works continued. Apartment access doors were installed. Ceramic flooring installation in common areas began. Thermal insulation works and facade finishing works continued. Exterior railings are being installed, and terrace flooring installation began;
Building 2: Plastering works and installation works continued. Tiling (floor and wall tiles) continued. Apartment access doors were installed. Thermal insulation works and facade finishing works continued. Exterior railings are being installed, and terrace flooring installation began;
Building 3: Plastering and skimming works continued, as did installation works. Ceramic tiling in bathrooms and kitchens continued. Apartment access doors were installed. Ceramic flooring installation in common areas began. Thermal insulation works and facade finishing works continued. Exterior railings are being installed.

June 2026

Building 1: Plastering and skimming works continued, as did installation works and ceramic tiling in bathrooms and kitchens. Washable painting works and installation of apartment access doors began. Thermal insulation works also continued, and facade finishing works began;
Building 2: Plastering and installation works continued. Underfloor heating installation works were completed, and screeds were poured. Tiling (floor and wall tiles) began. Thermal insulation works and facade finishing works also continued;
Building 3: Plastering and skimming works continued, as did installation works. Ceramic tiling in bathrooms and kitchens continued. Apartment access doors are being installed. Thermal insulation works and facade finishing works also continued.

May 2026

Building 1: Plastering and skimming works continued, as did installation works and ceramic tiling in bathrooms and kitchens. Screed and waterproofing works for terraces were completed. Thermal insulation works continued. Railings are being installed on the 4th floor;
Building 2: Plastering works and installation works continued. Underfloor heating installation works continued. Screed and waterproofing works for terraces were completed. Thermal insulation works and facade finishing works continued. Railings are being installed on the 4th floor;
Building 3: Plastering and skimming works continued, as did installation works. Ceramic tiling in bathrooms and kitchens continued. Thermal insulation works began. Railings are being installed on the 4th floor.

April 2026

Building 1: Plastering works, installation works, and ceramic tiling in bathrooms and kitchens continued. Screed and terrace waterproofing works are in progress. Thermal insulation works continued;
Building 2: Gypsum board partitioning works were completed. Plastering and installation works continued. Underfloor heating installation works began. Screed and terrace waterproofing works are in progress. Thermal insulation works continued;
Building 3: Plastering works and installation works continued. Underfloor heating system installation was completed, and screeds were poured. Terrace waterproofing works were completed. Ceramic tiling in bathrooms and kitchens began.

March 2026

Building 1: Plastering works and installation works continued. Ceramic tiling in bathrooms and kitchens began. Screed and terrace waterproofing works are in progress. Thermal insulation works continued;
Building 2: Gypsum board partitioning works and installation works continued. Plastering works began. Screed and terrace waterproofing works are in progress. Thermal insulation works began;
Building 3: Plastering works and installation works continued. Underfloor heating system installation continued, and screeds were poured. Screed and terrace waterproofing works are in progress.

February 2026

Building 1: Gypsum board partitioning works and installation works continued;
Building 2: Gypsum board partitioning works and installation works continued;
Building 3: Gypsum board partitioning works, installation works, and exterior joinery installation continued.

January 2026

Building 1: Gypsum board partitioning works and installation works continued. The underfloor heating system was installed, and screeds were poured on the first floors;
Building 2: Gypsum board partitioning works and installation works continued;
Building 3: Gypsum board partitioning works and installation works continued. Interior plastering works began.

December 2025

Building 1: Masonry works completed, gypsum board partitioning and installation works executed. Exterior joinery was installed, and thermal insulation works began;

Building 2: Masonry works completed, gypsum board partitioning and installation works executed;

Building 3: Masonry works completed, gypsum board partitioning and installation works executed; Exterior joinery is being installed.

November 2025

Building 1: Masonry works on the Ground Floor and Floors 1–4 have been completed. Gypsum board partitioning and installation works are currently underway. Exterior joinery installation has also begun;
Buildings 2 and 3: Masonry works and gypsum board partitioning continue.

October 2025

Building 1: Masonry works were completed on the ground floor and floors 1–4. Gypsum board partitioning and installation works are currently underway.

Buildings 2 and 3: Masonry works continue, and gypsum board partitioning has begun.

September 2025

In September, the following were completed:
– Reinforced concrete structure works for the B+GF+3F+4 Recessed building, for Buildings C1, C2, and C3, were completed;
– In Building 1, masonry works were carried out on the Ground Floor and Floors 1–2, and gypsum board partitioning works have now begun;
– In Buildings 2 and 3, masonry works were carried out on the Ground Floor.

August 2025

Masonry Works – Building C1:
– Ground Floor – completed;
– Mezzanine – completed;
– Floor 1 – completed;
– Floor 2 – in progress.

In progress:
Buildings C2 and C3 – Ground Floor Masonry
Building C1 – Floor 4 (recessed) – Rebar was installed for the slab above the recessed 4th floor;
Building C2 – Floor 4 – Vertical elements for floor 4 were reinforced;
Building C3 – Floor 3 – Formwork for the slab above floor 3 was completed.

July 2025

By July 31, 2025, the following were completed:
– Execution of reinforced concrete slab above Floor 3 and vertical elements for floor 4 – Building 1;
– Execution of reinforced concrete slab above Floor 2 and vertical elements for floor 3 – Building 2;
– Execution of concrete slab above Floor 2 – Building 3;
– Execution of masonry for ground floor, mezzanine, floor 1 – Building 1.

June 2025

By June 30, 2025, the following were completed:
– Execution of reinforced concrete slab above Floor 2 – Building 1;
– Execution of reinforced concrete slab above Floor 1 – Building 2;
– Execution of concrete slab above Mezzanine and above Floor 1 – Building 3.

May 2025

By May 31, 2025, the following were completed:
– Execution of reinforced concrete slab above Floor 1 – Building 1;
– Execution of reinforced concrete slab above Mezzanine – Building 2;
– Execution of reinforced concrete vertical elements for Mezzanine – Building 3.

April 2025

By April 30, 2025, the following were completed:
– Pouring of concrete into the reinforced concrete vertical elements of the mezzanine for Building 1;
– Formwork and partial reinforcement of the slab above the mezzanine for Building 1;
– Completion of reinforced concrete vertical elements (walls, columns) for the ground floor of Building 2;
– Execution of reinforced concrete slab above the ground floor for Building 2;
– Execution of reinforced concrete vertical elements for the mezzanine of Building 2;
– Execution of reinforced concrete vertical elements for the ground floor of Building 3.

March 2025

By March 31, 2025, the following were completed:
– Pouring of concrete into the reinforced concrete vertical elements of the ground floor for Building 1;
– Pouring of concrete into the slab above the ground floor for Building 1;
– Completion of reinforced concrete vertical elements (walls, columns) for the basement of Building 2;
– Pouring of concrete into the slab above the basement for Building 2;
– Partial execution of reinforced concrete vertical elements (walls, columns) for the ground floor of Building 2;
– Completion of reinforced concrete vertical elements (walls and columns) for the basement of Building 3;
– Pouring of concrete into the slab above the basement for Building 3;

February 2025

By February 28, 2025, the following were completed:
– Pouring of concrete into the vertical elements of the basement for Building 1;
– Pouring of concrete into the slab above the basement for Building 1;
– Partial execution of reinforced concrete vertical elements (walls, columns) for the basement of Building 2;
– Partial execution of reinforcement works for vertical elements (walls and columns) for the basement of Building 3.

January 2025

By January 31, 2025, the following were completed:
– Pouring of concrete into the raft foundations for Building C3;
– Partial execution of vertical elements (walls, columns) for the basement of Building 1.

December 2024

By December 31, 2024, the following were completed:
– Pouring of concrete into the raft foundations for Buildings C1 and C2;

November 2024

By November 30, 2024, the following were completed:
– General excavation;
– Pouring of leveling concrete.

October 2024

By October 31, 2024, site organization was completed, and works began